Fernbrook, UK

Modern Feeding and Digestion Technology in Action

This BIOGEST PowerDigest plant in Fernbrook is a successful extension of an existing facility and demonstrates the advantages of modern feeding and digestion technology.

Equipped with two PowerDigest units and a final storage tank, the plant processes approximately 65,000 tons of feedstock converting them into around 1,310 Nm³/h of biogas. Of this, roughly 758 Nm³/h is upgraded to biomethane and injected into the gas grid. A key highlight of the project is its advanced feeding system, which ensures efficient preparation and consistent delivery of all substrates into the digestion process. Compliance with the most up-to-date regulations for digestate are met though a dedicated system comprehending hygenization and separation steps. Fernbrook showcases the flexibility and scalability of the BIOGEST PowerDigest concept – making it a strong reference for sustainable and future-oriented biomethane production.

Fernbrook Biomethane Plant

  • 758 Nm3/h (224,232 MMBTU/year)
  • Over 65,000 tons food waste, organic waste, agricultural by-products, manure are processed per year

Project Timeline

  • October 2023: Start of earthworks
  • 17 months of construction
  • April 2025: First gas production